Nutrient removal addresses nitrogen and phosphorus, the nutrients that drive eutrophication in receiving waters. Municipal consents increasingly limit total nitrogen and total phosphorus. MBBR contributes strongly to nitrogen removal through combined nitrification and denitrification, but phosphorus removal with MBBR relies on chemical precipitation — the process does not perform enhanced biological phosphorus removal (EBPR) on its own.
Nitrogen Removal
Total nitrogen removal requires nitrification (ammonia to nitrate) followed by denitrification (nitrate to nitrogen gas). MBBR achieves this with staged aerobic and anoxic reactors: an aerobic stage nitrifies, and an anoxic stage denitrifies using a carbon source — either influent BOD via recycle or a dosed external carbon. Staging allows each population to develop on carriers optimised for its duty.
Phosphorus Removal
MBBR does not carry out enhanced biological phosphorus removal, which depends on cycling a suspended sludge through anaerobic and aerobic zones. For phosphorus, MBBR plants use chemical precipitation — dosing a metal salt to form an insoluble phosphate that is removed with the solids. This is a reliable, well-understood route to a low total-phosphorus effluent.
Municipal Nutrient Removal Design Context (indicative literature ranges — confirm per project)
| Parameter | Typical Value | Unit | Notes |
|---|---|---|---|
| Nitrogen route | nitrification + denitrification | — | Staged aerobic/anoxic |
| Denitrification carbon | internal or dosed | — | Site-specific — confirm per project |
| Phosphorus route | chemical precipitation | — | MBBR does not perform EBPR |
| Metal salt dose | stoichiometric + excess | — | Confirm by jar test / project |
A Combined Nutrient Strategy
A municipal plant meeting both nitrogen and phosphorus limits typically combines a staged nitrification/denitrification MBBR with chemical phosphorus precipitation. Defining the achievable targets and the carbon and chemical demands is a site-specific exercise that should be confirmed per project.
Frequently Asked Questions
Can MBBR remove total nitrogen?
Can MBBR remove phosphorus biologically?
How is phosphorus removed in an MBBR plant?