MBBR start-up is the process of establishing an active biofilm on new (virgin) carriers. Unlike activated sludge, which can be seeded with return sludge from another plant in hours, biofilm development takes time — heterotrophic biofilm for carbon removal can establish in one to three weeks, while a nitrifying biofilm may need four to eight weeks or longer depending on temperature and ammonia availability. Patient, controlled start-up avoids false starts and gets the reactor to full performance faster.
Start-up phases
Phase 1 — Inoculation and initial colonisation (Week 1–2): The reactor is filled with wastewater and aeration is started. Bacteria from the influent begin to attach to the carrier surfaces. Some operators seed the reactor with activated sludge from a nearby plant to accelerate colonisation, though this is not strictly necessary — the influent bacteria alone will colonise given time.
Phase 2 — Biofilm maturation (Week 2–4): A visible biofilm develops on the carriers. Carbon removal performance improves rapidly. The organic load can be gradually increased as the biofilm thickens and becomes more active. Monitoring effluent COD/BOD shows a declining trend.
Phase 3 — Nitrification onset (Week 4–8+): Nitrifying bacteria are slow-growing and establish after the heterotrophic biofilm. Effluent ammonia begins to drop as the nitrifying population builds up. Full nitrification can take 6–8 weeks at 15–20 °C; at lower temperatures it takes longer. During this phase, maintain adequate DO (≥3 mg/L) and alkalinity to support the nitrifiers.
Start-up timeline
Indicative start-up durations (confirm per project)
| Parameter | Typical Value | Unit | Notes |
|---|---|---|---|
| Carbon removal (heterotrophs) | 1–3 | weeks | Fast-growing; colonise first. |
| Nitrification (autotrophs) | 4–8+ | weeks | Slow-growing; temperature-dependent. |
| Full performance (combined) | 6–12 | weeks | Depends on T, load, seeding. |
| Seeding (activated sludge) | Optional | — | Can shorten colonisation by 1–2 weeks. |
| Start-up at <12 °C | Significantly longer | — | Cold slows all biological growth. |
Practical start-up tips
Start at reduced load (30–50 % of design) and ramp up gradually as performance improves. Monitor effluent quality daily during start-up. Maintain generous DO (≥4 mg/L) and ensure alkalinity is sufficient for nitrifiers. Avoid toxic slugs, large pH swings or extended periods without feed — the immature biofilm is more vulnerable to stress than a mature one. If possible, start in warm months to accelerate nitrifier establishment.
Frequently Asked Questions
Can start-up be accelerated?
What does the biofilm look like during start-up?
Should I monitor during start-up even if the plant is not yet at design load?