Healthy biofilm on carriers is the foundation of MBBR performance. When carriers are bare, patchy or developing only thin, easily-detached biofilm, the reactor cannot achieve design removal rates. Poor biofilm growth can occur during initial start-up (slow colonisation) or during operation (biofilm loss after a disturbance). The causes differ and so do the remedies.
Causes during start-up
New (virgin) carriers have a smooth surface that bacteria must colonise from scratch. This takes time — one to three weeks for heterotrophs, longer for nitrifiers. Factors that slow start-up colonisation include: cold temperature (biological growth is slower), intermittent or low wastewater feed (not enough substrate to sustain growth), and excessive aeration (high shear strips the fledgling biofilm before it can anchor). Patience and gentle conditions during start-up are key.
Causes during operation
If an established biofilm deteriorates, the most common causes are: toxic event (industrial discharge, chlorination, heavy metals) that kills the biofilm organisms; excessive shear from over-aeration or mechanical damage; prolonged starvation (no feed for extended periods, e.g. seasonal shutdown); and extreme pH or temperature excursions.
Cause–remedy matrix
Poor biofilm growth: causes and actions
| Parameter | Typical Value | Unit | Notes |
|---|---|---|---|
| Cold start-up (<12 °C) | Allow more time; seed if possible | — | Start in warm months if feasible. |
| Excessive shear (over-aeration) | Reduce airflow to minimum mixing | — | Protect fledgling biofilm. |
| Toxic inhibition | Identify & isolate source | — | Recovery may take weeks. |
| Insufficient substrate | Increase feed rate gradually | — | Biofilm needs BOD to grow. |
| Nutrient deficiency | Dose N, P if unbalanced | — | Industrial WW may lack nutrients. |
| Carrier surface issue | Rare; check carrier specification | — | Some coatings inhibit attachment. |
Frequently Asked Questions
Can I seed new carriers with biofilm from another MBBR?
How do I know if a toxic event caused the biofilm loss?
Should I increase organic loading to promote biofilm growth?